01 / PROJECT SUMMARY
What the public record shows.
Nebius Data Center is tracked in Independence, Jackson County, MO. The current public-record status is Approved / Permitted / Under Construction. The record identifies developer: Patmos; owner or tenant: Undisclosed. The reported capacity is 880 MW. This page cites 7 public sources.
Latest status detail: Independence expressly excluded the already-submitted or authorized Nebius project from its new 180-day moratorium.
- Site or address
- 2501 E Necessary Rd
- Developer
- Patmos
- Owner or tenant
- Undisclosed
- Expected online
- Not reported
- Project cost
- $150 billion
- Facility size
- 2,500,000 sq. ft.
- Property
- Not reported
- Purpose
- cloud, high-density compute, software and data center solutions.
- Community or watchdog record
- Petition organizers (name not reported in source field) | FracTracker Alliance (national project monitor)
- Activity or stance
- Community pushback documented; organization/stance may be unnamed
- Location confidence
- High
- Last source update
- 2026-07-06
“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.