01 / PROJECT SUMMARY
What the public record shows.
Lake Hawkeye Data Center is tracked in Lansing, Tompkins County, NY. The current public-record status is Proposed. The record identifies developer: TeraWulf; owner or tenant: Undisclosed. The reported capacity is 150 MW. This page cites 9 public sources.
Latest status detail: The plan would redevelop a former coal power plant as a data center with battery storage and more than 1 million sq. ft. Phase 1 covers the three western buildings; Phase 2 adds one larger building to the east.
- Site or address
- Miliken Station Rd
- Developer
- TeraWulf
- Owner or tenant
- Undisclosed
- Expected online
- Not reported
- Project cost
- Not reported
- Facility size
- 1,360,000 sq. ft.
- Property
- 183 acres
- Purpose
- Not reported
- Community or watchdog record
- Local community group (name not reported in source field) | FracTracker Alliance (national project monitor)
- Activity or stance
- Anti/concern/opposition activity documented
- Location confidence
- High
- Last source update
- 2026-05-11
“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.