SOURCED PROJECT RECORD · DCA-1010

Accokeek Center

Stafford, Stafford County, VA

Approved / Permitted / Under Construction122 MWreported capacity
SAVED PROJECTS + ALERTS

Follow this public record

Save what matters and receive in-site alerts when Project Watch records change.

My saved projects Get the monthly Ally Update

01 / PROJECT SUMMARY

What the public record shows.

Accokeek Center is tracked in Stafford, Stafford County, VA. The current public-record status is Approved / Permitted / Under Construction. The record identifies developer: Falmouth Tech LLC; owner or tenant: Undisclosed. The reported capacity is 122 MW. This page cites 4 public sources.

Latest status detail: The Stafford County Board of Supervisors approved the Accokeek Center rezoning and related action by a 4-3 vote on October 7, 2026. The approved plan covers two data center buildings totaling approximately 590,000 square feet on about 121 acres. Separate construction or operating status was not confirmed.

Site or address
RT 1/Interstate 95 South of Rappahannock Regional Jail
Developer
Falmouth Tech LLC
Owner or tenant
Undisclosed
Expected online
Not reported
Project cost
Not reported
Facility size
590,000 sq. ft.
Property
120.88 acres
Purpose
Not reported
Community or watchdog record
Protect Stafford and residents raised setback, land-use, water, traffic, and process concerns | FracTracker Alliance (national project monitor)
Activity or stance
Community concern and scrutiny documented
Location confidence
High
Last source update
2026-10-07
Evidence statusOfficially sourced
Source freshnessCurrent
Source links4
Completeness100%

“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.

03 / RECORD HISTORY

What changed.

Project Watch preserves prior and next record versions during each operational import. Records missing from a future update are retired, not silently deleted.

source_review

Status · Status detail · Reported capacity · Minimum MW · Maximum MW · facility Sq Ft · community Pushback · Community or watchdog record · Activity or stance · Additional sources · Source update date · Data-quality notes

source_review

Status detail · Additional sources · Source update date · Data-quality notes

update

Status detail · Developer · role Basis · facility Sq Ft · property Acres · Government sources · Meeting links · Primary source · location Confidence · Data-quality notes

Methodology

Prepared and reviewed by Jayson Hamilton for Your Data Center Ally. Records prioritize official government and permitting sources. Company, news, and community sources add context but do not replace the public docket. The national dataset is reviewed monthly.