SOURCED PROJECT RECORD · DCA-1049

Project Tembo (Previously "Project Jade")

Cheyenne, Laramie County, WY

Approved / Permitted / Under Construction2,700 resource mix incl. reserves MWreported capacity
SAVED PROJECTS + ALERTS

Follow this public record

Save what matters and receive in-site alerts when Project Watch records change.

My saved projects Get the monthly Ally Update

01 / PROJECT SUMMARY

What the public record shows.

Project Tembo (Previously "Project Jade") is tracked in Cheyenne, Laramie County, WY. The current public-record status is Approved / Permitted / Under Construction. The record identifies developer: Google; owner or tenant: Google. The reported capacity is 2,700 resource mix incl. reserves MW. This page cites 10 public sources.

Latest status detail: Black Hills Corp. signed definitive agreements effective September 30 to serve Google's planned Cheyenne data center. The utility says the project is not paused and expects energy service in late 2027, ramping to peak load in 2030. Crusoe is no longer the development partner.

Site or address
Switchgrass Industrial Park, west of I-85. 2 miles south of Terry Ranch Rd
Developer
Google
Owner or tenant
Google
Expected online
Late 2027 service; peak ramp by 2030
Project cost
Not reported
Facility size
Not reported
Property
1,375 acres
Purpose
Not reported
Community or watchdog record
FracTracker Alliance (national project monitor)
Activity or stance
Community pushback documented; organization/stance may be unnamed
Location confidence
High
Last source update
2026-10-06
Evidence statusOfficially sourced
Source freshnessCurrent
Source links10
Completeness100%

“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.

03 / RECORD HISTORY

What changed.

Project Watch preserves prior and next record versions during each operational import. Records missing from a future update are retired, not silently deleted.

source_review_skipped_newer_edit

Lifecycle change recorded.

update

Status · Status detail · Reported capacity · Minimum MW · Maximum MW · Developer · role Basis · Expected online date · Government sources · Additional sources · Source update date · Data-quality notes

source_review

Lifecycle change recorded.

source_review

Additional sources · Source update date · Data-quality notes

Methodology

Prepared and reviewed by Jayson Hamilton for Your Data Center Ally. Records prioritize official government and permitting sources. Company, news, and community sources add context but do not replace the public docket. The national dataset is reviewed monthly.