01 / PROJECT SUMMARY
What the public record shows.
Project Bus is tracked in Temple, Carroll and Haralson County, GA. The current public-record status is Suspended. The record identifies developer: Atlas Development; owner or tenant: Undisclosed. The reported capacity is Undisclosed MW. This page cites 5 public sources.
Latest status detail: Rezoning application withdrawn Feb 2026
- Site or address
- near Center Point Rd and Vaughn Rd
- Developer
- Atlas Development
- Owner or tenant
- Undisclosed
- Expected online
- 2036
- Project cost
- $11 billion
- Facility size
- Not reported
- Property
- 350 acres
- Purpose
- Not reported
- Community or watchdog record
- The Carroll County Anti-Data Center Coalition consists of local residents and officials opposing large-scale data center developments. Focused on protecting rural land, they argue these projects strain water/energy resources and threaten farmland preservation, with commissioners actively opposing new developments | FracTracker Alliance (national project monitor)
- Activity or stance
- Community pushback documented; organization/stance may be unnamed
- Location confidence
- Medium
- Last source update
- 2026-06-08
“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.