01 / PROJECT SUMMARY
What the public record shows.
Meta Bowling Green Data Center/ Project Accordion is tracked in Bowling Green, Wood County, OH. The current public-record status is Approved / Permitted / Under Construction. The record identifies developer: Meta; owner or tenant: Meta. The reported capacity is 514 MW. This page cites 8 public sources.
Latest status detail: Apollo Generating Station being built to supply this data center, which is a 350 megawatt (MW) natural gas fired electric generation facility. Two 16 inch gas pipelines will feed plant. Nearby land rezoning of 112 acres canceled (possible additional data center?) but rest of Meta project still on track.
- Site or address
- 20750 Midstar Dr
- Developer
- Meta
- Owner or tenant
- Meta
- Expected online
- 2027
- Project cost
- $800 million
- Facility size
- 715,000 sq. ft.
- Property
- 280 acres
- Purpose
- Not reported
- Community or watchdog record
- FracTracker Alliance (national project monitor)
- Activity or stance
- Community pushback documented; organization/stance may be unnamed
- Location confidence
- High
- Last source update
- 2026-06-05