01 / PROJECT SUMMARY

What the public record shows.

Adams Fork Harless Data Center is tracked in Holden, Mingo County, WV. The current public-record status is Proposed. The record identifies developer: TransGas Development, LLC; owner or tenant: Undisclosed. The reported capacity is 2,398.5 MW. This page cites 5 public sources.

Latest status detail: Identical proposal to the Adams Fork Data Center Energy Campus in Wharncliffe. Each facility would house 117 engines powered by natural gas, with 114 of those running full-time. If no gas is available, the engines would run on diesel that is stored in 40 tanks on-site. Total of 7 pods attached to the 117 power plant engines. Each pod holds two large buildings on the outer side, housing the data centers. In a May 2025 presentation posted to their website, parent company TransGas Development Systems, LLC stated that it plans to expand data center capacity between this site and its sister site to 9.8 GW.

Site or address
Off Twentytwo Mine Rd
Developer
TransGas Development, LLC
Owner or tenant
Undisclosed
Expected online
Not reported
Project cost
Not reported
Facility size
Not reported
Property
Not reported
Purpose
Not reported
Community or watchdog record
https://www.wvhighlands.org/article/despite-public-pushback-west-virginia-approves-air-quality-permits-for-data-center-energy-campus-in-mingo-county/? https://westvirginiawatch.com/2025/05/28/it-will-destroy-this-place-tucker-county-residents-fight-for-future-against-proposed-data-center/ | FracTracker Alliance (national project monitor)
Activity or stance
Anti/concern/opposition activity documented
Location confidence
High
Last source update
2026-04-22
Evidence statusOfficially sourced
Source freshnessStale
Source links5
Completeness100%

“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.

03 / RECORD HISTORY

What changed.

Project Watch preserves prior and next record versions during each operational import. Records missing from a future update are retired, not silently deleted.

update

Status detail

update

Government sources · Primary source · Additional sources

update

Status detail

Methodology