01 / PROJECT SUMMARY
What the public record shows.
Adams Fork Wharncliffe Data Center is tracked in Wharncliffe, Mingo County, WV. The current public-record status is Proposed. The record identifies developer: TransGas Development, LLC; owner or tenant: Undisclosed. The reported capacity is 2,398.5 MW. This page cites 6 public sources.
Latest status detail: Identical proposal to the Adams Fork Harless Data Center. Each facility would house 117 engines powered by natural gas, with 114 of those running full-time. If no gas is available, the engines would run on diesel that is stored in 40 tanks on-site. In a May 2025 presentation posted to their website, parent company TransGas Development Systems, LLC stated that it plans to expand data center capacity between this site and its sister site to 9.8 GW.
- Site or address
- 2002 Twisted Gun Rd
- Developer
- TransGas Development, LLC
- Owner or tenant
- Undisclosed
- Expected online
- Not reported
- Project cost
- Not reported
- Facility size
- Not reported
- Property
- Not reported
- Purpose
- Not reported
- Community or watchdog record
- Local community group (name not reported in source field) | FracTracker Alliance (national project monitor)
- Activity or stance
- Anti/concern/opposition activity documented
- Location confidence
- High
- Last source update
- 2026-04-22