01 / PROJECT SUMMARY
What the public record shows.
Ridgeline Microgrid is tracked in Davis, Tucker County, WV. The current public-record status is Approved / Permitted / Under Construction. The record identifies developer: Fundamental Data LLC; owner or tenant: Undisclosed. The reported capacity is 1,656 MW. This page cites 9 public sources.
Latest status detail: Proposed Fundamental Data data-center campus paired with the Ridgeline Power Station gas plant near Davis, WV.
- Site or address
- Off of US-48, near the City of Thomas
- Developer
- Fundamental Data LLC
- Owner or tenant
- Undisclosed
- Expected online
- Not reported
- Project cost
- Not reported
- Facility size
- Not reported
- Property
- 10,000 acres
- Purpose
- Not reported
- Community or watchdog record
- Petition targets WV microgrid bill enabling Ridgeline project. Project has generated significant organized opposition from local residents and environmental groups concerned about air pollution, tourism impacts, and microgrid legislation enabling the development. | FracTracker Alliance (national project monitor)
- Activity or stance
- Anti/concern/opposition activity documented
- Location confidence
- Medium
- Last source update
- 2025-12-08
“Officially sourced” means at least one government or permitting link is present. It does not mean the responsible jurisdiction has confirmed every field.